Deriner Dam and Hydropower Project
Country: Turkey
Project period: 1st Phase 1996 - 2001
Client: Stucky Consulting Engineers.
ERG Construction Company.
Investment amount: EUR 800,000,000
Description:
The Deriner Dam and Hydropower Project was constructed on the Coruh River in the north-eastern part of Turkey and consisted of a 260m high arch dam (3rd highest in the world at the time) and a hydropower plant with 600 MW installed capacity.
Services provided:
- Specialist studies on concrete technology
- Design of all site facilities
- Setup of a project information system
- Development of most economic work methodologies
- Assistance to contractor on project management
- Assistance for special equipment procurement