Nura River Clean-up Project
Country: Kazakhstan
Project period: 04/2004 - 08/2006
Client: Committee for Water Resources, The World Bank
Investment amount: EUR 660,000
Description:
The remediation design of the mercury contaminated river Nura, including flood plains, river banks and the former sludge disposal site Zhaur Swamp. An estimated 2 Mio m³ of contaminated soil have to be excavated and transported to a safe landfill site.
Services provided:
- Verification of data provided by previous studies
- Determination of the clean-up level
- General design of the clean-up methodology
- Detailed design of the clean-up works
- Preparation of Tender Documents
- Assistance in tender evaluation