Guideline Design of Skenderaj Wastewater Treatment Plant
Country: Kosovo
Project period: 08/2004 - 09/2004
Client: European Agency of Reconstruction - Kosovo
Investment amount: EUR 3,400,000
Description:
The aim of the project was to provide the outline design, drawings, technical specifications and estimated quantities of work to enable the EAR to let a contract for the construction of the works. Based on previous study reports the treatment process applied Imhoff tanks and biological treatment by trickling filters. Sludge treatment was undertaken by a static sludge thickener and sludge drying beds.
Services provided:
- Process engineering for treatment plant
- Guideline design of plant components
- Preparation of technical specifications and Bill of Quantities