Small Hydropower Plant Bergbahn Lofer
Страна: Austria
Период проекта: 06/2009 - 08/2009
Заказчик: Private Investor
Сумма инвестиций: EIR 5,000
Описание:
The client operates an existing snow making system in the project area. The aim of the Pre-Feasibility Study was to design the technical options and evaluate and opine the technical and economical feasibility of the extension by a Small Hydropower Plant of the existing snow making system and introduce this project to the local authorities.
Оказанные услуги:
- Design of technical options and construction works
- Evaluate the technical and economical feasibility
- Introduce the project to the local authorities